Taipingling Nuclear Power Plant Unit 2 Completes Hot Test

Note* - All images used are for editorial and illustrative purposes only and may not originate from the original news provider or associated company.

Subscribe

- Never miss a story with notifications

- Gain full access to our premium content

- Browse free from any location or device.

Media Packs

Expand Your Reach With Our Customized Solutions Empowering Your Campaigns To Maximize Your Reach & Drive Real Results!

– Access the Media Pack Now

– Book a Conference Call

Leave Message for Us to Get Back

Related stories

DOE Selects 11 Projects for Nuclear Reactor Pilot Program

The U.S. Department of Energy (DOE) has formally launched...

Aramco Signs $11b Jafurah Midstream Deal With GIP Consortium

Jafurah Midstream Gas Company has secured a major foreign...

Equinix Enters Nuclear Deal With SMR Developers to Power DCs

In an effort to diversify its power portfolio, global...

SDIC Power Plans UK’s Largest Wind Turbines at Inch Cape

A Chinese state-owned enterprise is preparing to install the...

At Unit 2 of the Taipingling nuclear power plant in China’s Guangdong province, engineers have finished a critical round of testing designed to simulate the heat and pressure the reactor will face during normal operations. This is the second HPR1000, or Hualong One, reactor being developed at the site, which is eventually planned to house six such units.

“On 30 July, with the drainage of the primary circuit of Unit 2 of the Taipingling nuclear power plant to the circuit water level and the successful completion of the last test of Phase II.3, it marked the successful completion of the hot performance test, and the unit took another step towards the goal of high-quality commissioning,” China General Nuclear (CGN) said.

This phase of testing, known as hot functional testing, raises the reactor coolant system to high temperatures to check whether coolant channels and critical safety systems are functioning exactly as designed. These tests are carried out before any nuclear fuel is introduced into the system and are a vital part of confirming whether both the nuclear island and conventional equipment and systems meet their design requirements.

Earlier in the year, the plant completed cold functional testing at Taipingling 2. These assessments focused on ensuring that all safety-related components were installed correctly and could perform their roles in a cold condition. This round of checks was also the first time that the main reactor systems operated in conjunction with supporting auxiliary systems. The key aim was to verify the leak-tightness of the primary circuit.

Eventually, the Taipingling nuclear power plant will be home to six Hualong One reactor. Work began on the first two units in 2019 and 2020. Unit 1 completed its hot testing back in September 2024 and is expected to start up in 2025, with Unit 2 to follow in 2026.

In December 2023, China’s State Council approved the second phase of the project, which includes Units 3 and 4. Construction on Unit 3 got underway in June of this year.

Latest stories

Related stories

DOE Selects 11 Projects for Nuclear Reactor Pilot Program

The U.S. Department of Energy (DOE) has formally launched...

Aramco Signs $11b Jafurah Midstream Deal With GIP Consortium

Jafurah Midstream Gas Company has secured a major foreign...

Equinix Enters Nuclear Deal With SMR Developers to Power DCs

In an effort to diversify its power portfolio, global...

SDIC Power Plans UK’s Largest Wind Turbines at Inch Cape

A Chinese state-owned enterprise is preparing to install the...

Subscribe

- Never miss a story with notifications

- Gain full access to our premium content

- Browse free from any location or device.

Media Packs

Expand Your Reach With Our Customized Solutions Empowering Your Campaigns To Maximize Your Reach & Drive Real Results!

– Access the Media Pack Now

– Book a Conference Call

– Leave Message for Us to Get Back