Dutch network operators strike solar agreement to accelerate grid connections

Note* - All images used are for editorial and illustrative purposes only and may not originate from the original news provider or associated company.

Subscribe

- Never miss a story with notifications

- Gain full access to our premium content

- Browse free from any location or device.

Media Packs

Expand Your Reach With Our Customized Solutions Empowering Your Campaigns To Maximize Your Reach & Drive Real Results!

– Access the Media Pack Now

– Book a Conference Call

– Leave Message for Us to Get Back

Related stories

Rio Grande LNG Work Worth $9 Bn Awarded to Bechtel

A news release from the Houston-based oil and gas...

US Utilities, Energy Groups Back Clean Energy Tax Credits

In the US, 18 trade associations, which represent utilities,...

Customized Financing a Need for Distributed Renewable Energy

Tracking SDG 7: The Energy Progress Report 2025 goes...

Network operators in the Netherlands have struck an agreement with the country’s solar sector to speed-up grid connections for solar projects.

Under the terms of the deal, enshrined within a legal covenant, solar operators will agree to solar export limits of 70% of any given project’s peak generation capacity, a measure which grid operators said would allow for grid connection times to be slashed.

Trade body Holland Solar said the agreement would allow for solar to generate more efficiently and more affordably on the Dutch grid, adding that an influx of large solar projects in the Netherlands in recent years had resulted in various costly network upgrades to be required.

While those upgrades take place, solar – and other energy generation projects – are left waiting to connect to the grid, and the implementation of a 70% cap on exports is considered to reduce the need for those upgrades.

While grid connection agreements must be made at a project’s maximum peak generation capacity to ensure grid stability, Holland Solar stated that solar projects only produce more than 70% of that peak capacity for around 3% of the time. In capping exports to 70% of a project’s peak capacity, it’s aimed that more ‘space’ on grids will be identified and used to approve the connection of more solar.

Network operators have too agreed to provide more insight into particular areas of the grid which are more constrained, identifying where bottlenecks may be arising.

Meanwhile, Holland Solar’s members have also agreed to an amendment which states that all grid connection agreements are signed for a minimum of 20 years to ensure any investment in grid upgrades is justified.

In addition to the agreement, all parties involved have expressed their desire to see a separate category within the Netherlands’ SDE++ subsidy programme to provide additional support for renewables projects which “flatten the curve” of generation, such as those featuring energy storage applications.

Eric Wiebes, minister of economic affairs and climate in the Dutch government, welcomed the agreement, stating the energy transition presents us with the challenge “not only to generate more sustainable energy, but also in such a way that we can use this energy properly on our electricity grid”.

Latest stories

Related stories

Rio Grande LNG Work Worth $9 Bn Awarded to Bechtel

A news release from the Houston-based oil and gas...

US Utilities, Energy Groups Back Clean Energy Tax Credits

In the US, 18 trade associations, which represent utilities,...

Customized Financing a Need for Distributed Renewable Energy

Tracking SDG 7: The Energy Progress Report 2025 goes...

Subscribe

- Never miss a story with notifications

- Gain full access to our premium content

- Browse free from any location or device.

Media Packs

Expand Your Reach With Our Customized Solutions Empowering Your Campaigns To Maximize Your Reach & Drive Real Results!

– Access the Media Pack Now

– Book a Conference Call

– Leave Message for Us to Get Back