The station was shut down automatically when a 5.8-magnitude earthquake occurred on the East Coast of the US on 23 August this year.Dominion said it will first bring the facility’s Unit 1 online safely, and then begin the process for the second unit.Both units will take ten days to return to 100% operational mode.The company undertook a $21m programme of inspections, testing and analysis to make sure the station had no functional damage.
ย







![NextFloat Project Secures EIA Approval for Mediterranean Test Site Infographic about NextFloat Project securing EIA approval for a Mediterranean offshore test site, listing milestones and an 8.5 MW deployment.]](https://www.powerinfotoday.com/wp-content/uploads/2026/07/nextfloat-project-218x150.webp)