Australia’s largest hybrid microgrid project completes Stage 1

Note* - All images used are for editorial and illustrative purposes only and may not originate from the original news provider or associated company.

Subscribe

- Never miss a story with notifications

- Gain full access to our premium content

- Browse free from any location or device.

Media Packs

Expand Your Reach With Our Customized Solutions Empowering Your Campaigns To Maximize Your Reach & Drive Real Results!

– Access the Media Pack Now

– Book a Conference Call

Leave Message for Us to Get Back

Related stories

J&V Energy Expands Renewable Capacity with 187MW Solar Acquisition

J&V Energy Technology Co., Ltd. has officially reached an...

Fuel Storage Systems and Industrial Tank Infrastructure Management

Fuel storage systems are a foundational component of modern...
- Advertisement -

juwi Renewable Energy, the Australian subsidiary of international project developer juwi, has completed the first stage of the 23 MW hybrid power station, which will be Australia’s largest once completed.

In a statement, the firm noted that the hybrid system integrates solar photovoltaic (PV) with gas and diesel generation, to power Gold Fields’ Agnew gold mine, in Western Australia.

“We have successfully completed the first stage of the development of one of Australia’s largest hybrid renewable microgrid projects,” said Dave Manning, global head of Hybrid for juwi Renewable Energy.

Stage one included a 4 MW Single Axis Tracking PV installation together with cloud forecasting and an advanced microgrid control system to enable integration with the mine off-grid network.

The power station integrates 4 MW solar generation from the solar farm and is underpinned by 19 MW of gas and diesel generation. It will soon include other renewable energy technologies coming online in the next stage of the project.

The second stage of the project, which includes 18 MW of wind generation, a 13 MW battery and an advanced microgrid control system, is currently under construction and due to be completed in mid-2020.

EDL CEO, James Harman, said: “With this project, EDL and Gold Fields are leading the way towards clean, renewable energy to power remote, off-grid mining operations without compromising reliability or power quality.”

Valued at AUS$112 million ($76 million), the project has significant implications for hybrid deployment in the mining industry.

“Hybrid technology is proving to be an intelligent and efficient solution towards securing energy security, optimising energy costs and reducing carbon footprint,” said Manning.

The project has the backing of the Australian Renewable Energy Agency with a recoupable AUS$13.5 million contribution to the construction cost of the project.

Once completed, the Agnew Hybrid Renewable project will be the first to use wind generation as part of a large hybrid micro-grid in the Australian mining sector.

It will have a total installed generation capacity of 54 MW, with renewables providing over 50 per cent of the Agnew gold mine’s power requirements, with the potential to increase this further by adopting innovative operational practices such as the dynamic load shedding, renewables forecasting and load control management.

Power Info Today brings together the global energy industry — from generation and transmission operators to utility executives and energy transition leaders — through trusted editorial, market intelligence, and digital engagement.

Our 2026 Media Pack offers integrated solutions to reach your audience:

  • Magazine & Digital Editions Showcase your brand within premium energy industry coverage read by executives and decision - makers worldwide.
  • Industry Insights & Reports Align with data - driven analysis, trend reports, and regional roundups across the global power and energy value chain.
  • Brand Authority & Credibility Position your company as a thought leader through expert commentary, interviews, and special features.

Latest stories

Related stories

J&V Energy Expands Renewable Capacity with 187MW Solar Acquisition

J&V Energy Technology Co., Ltd. has officially reached an...

Fuel Storage Systems and Industrial Tank Infrastructure Management

Fuel storage systems are a foundational component of modern...

UK Offshore Wind Strategy Pushes for 5 GW Annual Capacity

The United Kingdom must commission a minimum of 5...

Subscribe

- Never miss a story with notifications

- Gain full access to our premium content

- Browse free from any location or device.

Media Packs

Expand Your Reach With Our Customized Solutions Empowering Your Campaigns To Maximize Your Reach & Drive Real Results!

– Access the Media Pack Now

– Book a Conference Call

Leave Message for Us to Get Back

Translate »